Project experience Sewage treatment
System experience Vertical flow reedbeds
Year completed 2013
Client Thames Water
Consultant ARM Ltd
Contractor Black and Veatch
 
 

Challenge

Lower Basildon WwTW is owned and operated by Thames Water and is situated within the grounds of Beale Park seven miles North West of Reading. The works serves a PE 166 (2011 – Average). Sewage is collected by gravity and conveyed to a coarse screen within a small rectangular chamber at the works. Screened sewage is then passed to six buried soak-away units. These tend to pool and flood during periods of high load.

The existing site has historically had no discharge consent, however, in 2011 the Environmental Agency (EA) introduced an indicative discharge consent of 30/45/5 (BOD/SS/NH3 mg/l) for groundwater. The groundwater consent was considered ‘tight’ and hence an indicative 95%ile new river discharge consent of 40/60 (BOD/SS mg/l) was also proposed to be effective from March 2014. The existing WwTW at Lower Basildon was unable to meet the requirement of either of the proposed consents and therefore Thames Water accepted the need for renewal of the current works under the quality driver for the future discharge to the River Thames.

The scope that was required to be delivered by the subcontractor for Lower Basildon sewage treatment works include outline design, detailed design and construction of a new sewage works adjacent to the existing Lower Basildon site, constructed and commissioned to the 2026 design horizon. The works was to be designed and constructed by the subcontractor as a ‘turn-key’ package as per the requirements of all applicable Thames Water standards. ARM Ltd was requested by Thames water contractor Black and Veatch to provide a suitable solution bearing in mind no power availability on site.

Solution

The lack of power on site eliminated the potential for an aerated system which would minimise area requirements, so a passive treatment solution was sought. ARM Ltd installed a 40m3 septic tank followed by a COPASAC chamber (with bypass), a siphon chamber for batch flow generation and a 684m2 passive, vertical flow reed bed system which would discharge into the local water course.

Benefits

The wastewater treatment system installed provides Thames Water with the required no power solution for achieving the new consents specified by the EA based on loads predicted for 2026. Secure treatment has been provided with a minimal carbon footprint which is aesthetically appropriate for its location within a visitor park.


Challenge

Lower Basildon WwTW is owned and operated by Thames Water and is situated within the grounds of Beale Park seven miles North West of Reading. The works serves a PE 166 (2011 – Average). Sewage is collected by gravity and conveyed to a coarse screen within a small rectangular chamber at the works. Screened sewage is then passed to six buried soak-away units. These tend to pool and flood during periods of high load.

The existing site has historically had no discharge consent, however, in 2011 the Environmental Agency (EA) introduced an indicative discharge consent of 30/45/5 (BOD/SS/NH3 mg/l) for groundwater. The groundwater consent was considered ‘tight’ and hence an indicative 95%ile new river discharge consent of 40/60 (BOD/SS mg/l) was also proposed to be effective from March 2014. The existing WwTW at Lower Basildon was unable to meet the requirement of either of the proposed consents and therefore Thames Water accepted the need for renewal of the current works under the quality driver for the future discharge to the River Thames.

The scope that was required to be delivered by the subcontractor for Lower Basildon sewage treatment works include outline design, detailed design and construction of a new sewage works adjacent to the existing Lower Basildon site, constructed and commissioned to the 2026 design horizon. The works was to be designed and constructed by the subcontractor as a ‘turn-key’ package as per the requirements of all applicable Thames Water standards. ARM Ltd was requested by Thames water contractor Black and Veatch to provide a suitable solution bearing in mind no power availability on site.

Solution

The lack of power on site eliminated the potential for an aerated system which would minimise area requirements, so a passive treatment solution was sought. ARM Ltd installed a 40m3 septic tank followed by a COPASAC chamber (with bypass), a siphon chamber for batch flow generation and a 684m2 passive, vertical flow reed bed system which would discharge into the local water course.

Benefits

The wastewater treatment system installed provides Thames Water with the required no power solution for achieving the new consents specified by the EA based on loads predicted for 2026. Secure treatment has been provided with a minimal carbon footprint which is aesthetically appropriate for its location within a visitor park.


Interested in this project?
Call 01889 583811
OR
 
 
 
Downloads
  • Brochure - Vertical flow reed beds
    Brochure - Vertical flow reed beds
    2pp 217.52KB
    Download
  • ARM Asset Management service
    ARM Asset Management service
    294.83KB
    Download
  • Case study: Lower Basildon
    Case study: Lower Basildon
    2pp 231.63KB
    Download
 
 
 
Enquire
 


Related entries

  • ARM Ltd: Award-winning passive reed beds - it's not all about FBA
    Award-winning passive reed beds - it's not all about FBA
    ARM Ltd
    Whilst Forced Bed Aeration™ (FBA™) has increased wetland capabilities by up to fifteen times that of a traditional reed bed, passive reed beds are the most popular natural solution when there is no power on site. Lower...
  • ARM Ltd: Reedbed asset assessment and support services
    Reedbed asset assessment and support services
    ARM Ltd
    Knowledge and proactive management of remote reedbeds is a key area where companies can cut operational and capital expenditure. The optimisation and enhancement of remote reedbed treatment systems can secure performance for...
  • ARM Ltd: Vertical flow reedbeds
    Vertical flow reedbeds
    ARM Ltd
    ARM Ltd specialises in natural wastewater treatment systems using constructed wetland technology, including vertical flow reedbeds. Unsaturated vertical flow (VF) systems are essentially the same as the horizontal flow...
  • ARM Ltd: Thames Water invests in FBA™ reed bed
    Thames Water invests in FBA™ reed bed
    ARM Ltd
    The UK’s largest water company has invested in a new reed bed system to help manage wastewater at its treatment facility in Uffington, Oxfordshire. Thames Water Limited appointed Rugeley-based reed bed specialists, ARM Reed...
Not found what you're looking for? View other options

Ask ARM Ltd about

Vertical flow reedbed: municipal effluent