Challenge

Uffington Waste Water Treatment Works (WwTW), operated by Thames Water, serves a population of 700-800 in a rural situation. The WwTW comprised a primary settlement tank, filter bed and humus tank.

Due to its age and an increasing load from the village the works required chemical coagulant dosing to improve load removal through precipitation, settlement and filtration.

The site was starting to breach consents occasionally and Thames Water was aware that discharge limits for the WwTW were likely to be tightened in the next few years. This would potentially require the need to upgrade the whole site. The cost of chemical dosing was also significant on what is a relatively small site. Average flows were 174m3/day with a maximum of 347m3/day; average loadings to the works are 45kg/d BOD and 6kg/d ammonia.

The BOD discharge was approaching consent whilst the solids and ammonia were in breach of consent.

Solution

Rather than refurbishing or replacing the whole works ARM Ltd provided Thames Water with a long-term solution through the design and installation of an Aerated Saturated Vertical Flow reedbed to operate as a tertiary final polishing system. The vertical flow orientation minimised the footprint of the required bed whilst the aeration provided enhanced microbial treatment to bring the BOD, suspended solids and ammonia site discharges comfortably into consent.

Two beds were installed, with a total footprint of 550m2.

Outcome

The Forced Bed Aeration™ solution provided by ARM Ltd saved Thames Water the capital costs of complete replacement or refurbishment of the works whilst providing them with a long-term low maintenance, low carbon footprint solution which not only secures consents but blends into the rural location providing additional biodiversity and amenity.


Challenge

Uffington Waste Water Treatment Works (WwTW), operated by Thames Water, serves a population of 700-800 in a rural situation. The WwTW comprised a primary settlement tank, filter bed and humus tank.

Due to its age and an increasing load from the village the works required chemical coagulant dosing to improve load removal through precipitation, settlement and filtration.

The site was starting to breach consents occasionally and Thames Water was aware that discharge limits for the WwTW were likely to be tightened in the next few years. This would potentially require the need to upgrade the whole site. The cost of chemical dosing was also significant on what is a relatively small site. Average flows were 174m3/day with a maximum of 347m3/day; average loadings to the works are 45kg/d BOD and 6kg/d ammonia.

The BOD discharge was approaching consent whilst the solids and ammonia were in breach of consent.

Solution

Rather than refurbishing or replacing the whole works ARM Ltd provided Thames Water with a long-term solution through the design and installation of an Aerated Saturated Vertical Flow reedbed to operate as a tertiary final polishing system. The vertical flow orientation minimised the footprint of the required bed whilst the aeration provided enhanced microbial treatment to bring the BOD, suspended solids and ammonia site discharges comfortably into consent.

Two beds were installed, with a total footprint of 550m2.

Outcome

The Forced Bed Aeration™ solution provided by ARM Ltd saved Thames Water the capital costs of complete replacement or refurbishment of the works whilst providing them with a long-term low maintenance, low carbon footprint solution which not only secures consents but blends into the rural location providing additional biodiversity and amenity.


Interested in this project?
Call 01889 583811
OR
 
 
 
Downloads
  • Case Study: Uffington WwTW
    Case Study: Uffington WwTW
    2pp 3.64MB
    Download
  • Brochure - Vertical flow reed beds
    Brochure - Vertical flow reed beds
    2pp 217.52KB
    Download
  • Article: Reed bed treatment solution
    Article: Reed bed treatment solution
    10pp 1.25MB
    Download
 
 
 
Enquire
 


Related entries

  • ARM Ltd: Reedbed asset assessment and support services
    Reedbed asset assessment and support services
    ARM Ltd
    Knowledge and proactive management of remote reedbeds is a key area where companies can cut operational and capital expenditure. The optimisation and enhancement of remote reedbed treatment systems can secure performance for...
  • ARM Ltd: Forced Bed Aeration™ for wetland wastewater treatment
    Forced Bed Aeration™ for wetland wastewater treatment
    ARM Ltd
    Forced Bed Aeration™ (FBA™) is a technology designed to enhance the performance of wetlands for the treatment of high-strength wastewaters. The FBA™ system blows air through the wetland system. The increased presence of...

Also by ARM Ltd

ARM Ltd address and contact details

ARM Ltd
Rydal House
Colton Road
Rugeley
WS15 3HF
Tel: 01889 583811
Fax: 01889 584998
View on map
 
Follow ARM Ltd
 
Not found what you're looking for? View other options

Ask ARM Ltd about

Aerated saturated vertical flow reedbed for Thames Water