System experience Vertical flow reedbeds
Services Construction
Year completed 2014
Client Welsh Water
Contractor ARM Ltd
 
 

Challenge

Kingstone and Madley Waste Water Treatment Works, operated by Welsh Water, was constructed in the late 1940's and has been modified on several occasions over the years to accommodate the increasing population in the area.

In the late 1980's four parallel horizontal flow passive reedbeds were added to the system to provide a tertiary polish to the effluent prior to discharge to the local watercourse. These have performed well and are still in operation with discharge consent levels generally being maintained, though there has been some loss of treatment capacity due to age and increased loading rates resulting in the short circuiting of flow across the reedbed surface.

Further predicted increases in local population and tightening discharge consents led to a review of the treatment process across the whole works to ensure compliant treatment of the additional loads. As a result a full site refurbishment and filter replacement was planned. Welsh Water was keen to employ existing assets were possible and, therefore, asked ARM Ltd to provide proposals for a reedbed refurbishment and upgrade.

The average daily flow to the reedbeds is 332m3 with a peak flow of 16.6 l/sec. 

Solution

Following a site review ARM Ltd determined that with the use of Forced Bed Aeration™ (FBA™) only two of the four existing horizontal flow beds (approximately 1500m2 total) would be required to treat the post refurbishment design load to the required consent levels. The chosen beds were in a very poor condition and would require complete refurbishment themselves including liner replacement, new media, distribution / collection system, duty / standby blowers and conversion from horizontal flow to saturated vertical flow operation.

The new system was designed based on the upstream process consisting of a primary settlement tank, refurbished trickling filters and humus tank.

Effluent from the existing system is now fed into a newly built direction chamber which feeds into the retrofitted reedbeds.

Delivered within just four months ARM Ltd was also able to keep the site fully operational which was vital for the uninterrupted treatment of wastewater.

Outcome

The new FBA™ treatment reedbed provides Welsh Water with a robust, secure, high performance, tertiary treatment capability at the Kingstone and Madley site providing long term compliance.

Because only two of the beds were used the remaining two beds offer additional passive treatment if required and potential for significant additional capacity if refurbished.


Challenge

Kingstone and Madley Waste Water Treatment Works, operated by Welsh Water, was constructed in the late 1940's and has been modified on several occasions over the years to accommodate the increasing population in the area.

In the late 1980's four parallel horizontal flow passive reedbeds were added to the system to provide a tertiary polish to the effluent prior to discharge to the local watercourse. These have performed well and are still in operation with discharge consent levels generally being maintained, though there has been some loss of treatment capacity due to age and increased loading rates resulting in the short circuiting of flow across the reedbed surface.

Further predicted increases in local population and tightening discharge consents led to a review of the treatment process across the whole works to ensure compliant treatment of the additional loads. As a result a full site refurbishment and filter replacement was planned. Welsh Water was keen to employ existing assets were possible and, therefore, asked ARM Ltd to provide proposals for a reedbed refurbishment and upgrade.

The average daily flow to the reedbeds is 332m3 with a peak flow of 16.6 l/sec. 

Solution

Following a site review ARM Ltd determined that with the use of Forced Bed Aeration™ (FBA™) only two of the four existing horizontal flow beds (approximately 1500m2 total) would be required to treat the post refurbishment design load to the required consent levels. The chosen beds were in a very poor condition and would require complete refurbishment themselves including liner replacement, new media, distribution / collection system, duty / standby blowers and conversion from horizontal flow to saturated vertical flow operation.

The new system was designed based on the upstream process consisting of a primary settlement tank, refurbished trickling filters and humus tank.

Effluent from the existing system is now fed into a newly built direction chamber which feeds into the retrofitted reedbeds.

Delivered within just four months ARM Ltd was also able to keep the site fully operational which was vital for the uninterrupted treatment of wastewater.

Outcome

The new FBA™ treatment reedbed provides Welsh Water with a robust, secure, high performance, tertiary treatment capability at the Kingstone and Madley site providing long term compliance.

Because only two of the beds were used the remaining two beds offer additional passive treatment if required and potential for significant additional capacity if refurbished.


Interested in this project?
Call 01889 583811
OR
 
 
 
Downloads
  • Brochure - Vertical flow reed beds
    Brochure - Vertical flow reed beds
    2pp 217.52KB
    Download
  • Article: Reed bed treatment solution
    Article: Reed bed treatment solution
    10pp 1.25MB
    Download
  • Case study: Kingston & Madley, Welsh Water
    Case study: Kingston & Madley, Welsh Water
    2pp 275.01KB
    Download
  • Forced Bed Aeration™ technology
    Forced Bed Aeration™ technology
    2pp 347.3KB
    Download
 
 
 
Enquire
 


Related entries

  • ARM Ltd: Reedbed asset assessment and support services
    Reedbed asset assessment and support services
    ARM Ltd
    Knowledge and proactive management of remote reedbeds is a key area where companies can cut operational and capital expenditure. The optimisation and enhancement of remote reedbed treatment systems can secure performance for...
  • ARM Ltd: Forced Bed Aeration™ for wetland wastewater treatment
    Forced Bed Aeration™ for wetland wastewater treatment
    ARM Ltd
    Forced Bed Aeration™ (FBA™) is a technology designed to enhance the performance of wetlands for the treatment of high-strength wastewaters. The FBA™ system blows air through the wetland system. The increased presence of...
Not found what you're looking for? View other options

Ask ARM Ltd about

Aerated saturated vertical flow reedbed for Welsh Water