Sector Utilities
Project type Refurbishment
Services provided Design
Contractor Carillion Water
Products used 21,000 cubic metres of BIOdek cross fluted media
 
 

Context

A UK water company needed to update the secondary treatment system at one of its large municipal sewage treatment works. The work, run by contractors Carillion Water, was part of a £12.5m AMP4 contract to upgrade the system and Carillion opted for a modular plastic media trickling filter solution, awarding the contract to supply the 21,000 cubic metres of BIOdek 150m2/m3 media to 2H Water Technologies.

This represented the largest single order for plastic media in Europe and reflects 2H’s ability to deliver robust and reliable water treatment solutions.

Process

Transporting this volume of media to site would have required 333 articulated trucks. Due to the flexibility of 2H’s assembly technology, however, the media was constructed on-site using the 2H unique thermal welding process to reduce costs. This avoided the use of adhesives and eliminated the emission of organic solvents which reduced the carbon footprint by 89,300kg CO2.

The material of construction of the media was also changed from PVC to polypropylene (PP) to prevent 120 tonnes of solvent required to chemically weld the PVC from entering the atmosphere on the site. There was also a saving on generating the electrical power required to run four gluing machines and their associated ventilation systems which would have added a further 19,000kg CO2 to the atmosphere.

The site facility to house the PP welding machines was constructed using a marquee standing on a hardcore base topped with asphalt. The four welding machines were installed inside the marquee and connected to a generator and compressor sited outside providing the power and air to run the welding machines and light the working area. Part of the area inside the marquee was used for storage of the foils that were to be welded into the finished modules. The power supply for on-site production created 32,300kg CO2 discharge, however the production on site gave an overall saving of 249,700kg CO2 .

The modules, ready for installation in the concrete tanks, were strapped to pallets which were stored on the 2,000 square metre area allocated to storage adjacent to the production facility. The media was installed in the 8 tanks above a support system of dwarf walls and concrete lintels. The modules were moved across the site by truck, still on their pallets and then lifted by crane into the tank for installation.

Outcome

“2H’s solution was ideal to address the stringent levels of environmental compliance required for this project. With such large filters (30.5 metres in diameter) it was crucial to identify a solution that worked efficiently at high loading. BIOdek plastic structured cross flow media‘s high active surface area is ideally suited to form deep beds. Each of the eight Trickling Filters contains a 3.6m deep bed of plastic media." - Bob Lorenzo, Regional Director, Carillion Water

“The need to improve levels of biological treatment efficiency will be achieved by 2H’s proven BIOdek media technology with eight Trickling Filters operating in parallel. At the same time, the structured cross flow nature of the BIOdek ensures that all the available surface area is utilised for the process. We are very pleased to win such a significant order.” - John Gattley, Managing Director, 2H Water Technologies Ltd


Context

A UK water company needed to update the secondary treatment system at one of its large municipal sewage treatment works. The work, run by contractors Carillion Water, was part of a £12.5m AMP4 contract to upgrade the system and Carillion opted for a modular plastic media trickling filter solution, awarding the contract to supply the 21,000 cubic metres of BIOdek 150m2/m3 media to 2H Water Technologies.

This represented the largest single order for plastic media in Europe and reflects 2H’s ability to deliver robust and reliable water treatment solutions.

Process

Transporting this volume of media to site would have required 333 articulated trucks. Due to the flexibility of 2H’s assembly technology, however, the media was constructed on-site using the 2H unique thermal welding process to reduce costs. This avoided the use of adhesives and eliminated the emission of organic solvents which reduced the carbon footprint by 89,300kg CO2.

The material of construction of the media was also changed from PVC to polypropylene (PP) to prevent 120 tonnes of solvent required to chemically weld the PVC from entering the atmosphere on the site. There was also a saving on generating the electrical power required to run four gluing machines and their associated ventilation systems which would have added a further 19,000kg CO2 to the atmosphere.

The site facility to house the PP welding machines was constructed using a marquee standing on a hardcore base topped with asphalt. The four welding machines were installed inside the marquee and connected to a generator and compressor sited outside providing the power and air to run the welding machines and light the working area. Part of the area inside the marquee was used for storage of the foils that were to be welded into the finished modules. The power supply for on-site production created 32,300kg CO2 discharge, however the production on site gave an overall saving of 249,700kg CO2 .

The modules, ready for installation in the concrete tanks, were strapped to pallets which were stored on the 2,000 square metre area allocated to storage adjacent to the production facility. The media was installed in the 8 tanks above a support system of dwarf walls and concrete lintels. The modules were moved across the site by truck, still on their pallets and then lifted by crane into the tank for installation.

Outcome

“2H’s solution was ideal to address the stringent levels of environmental compliance required for this project. With such large filters (30.5 metres in diameter) it was crucial to identify a solution that worked efficiently at high loading. BIOdek plastic structured cross flow media‘s high active surface area is ideally suited to form deep beds. Each of the eight Trickling Filters contains a 3.6m deep bed of plastic media." - Bob Lorenzo, Regional Director, Carillion Water

“The need to improve levels of biological treatment efficiency will be achieved by 2H’s proven BIOdek media technology with eight Trickling Filters operating in parallel. At the same time, the structured cross flow nature of the BIOdek ensures that all the available surface area is utilised for the process. We are very pleased to win such a significant order.” - John Gattley, Managing Director, 2H Water Technologies Ltd


Interested in this project?
Call 0845 003 9114
OR
 
 
 
Downloads
  • PLASdek® / BIOdek® cross-fluted fills
    PLASdek® / BIOdek® cross-fluted fills
    2pp 420 KB
    Download
  • PLASdek® / BIOdek® cross-fluted fills
    PLASdek® / BIOdek® cross-fluted fills
    2pp 420 KB
    Download
 
 
 
Enquire
 


Related entries

  • Enexio UK Ltd: BIOdek® cross-fluted fills
    BIOdek® cross-fluted fills
    Enexio UK Ltd
    BIOdek® cross-fluted fills for biological processes in water and waste water treatment 2H BIOdek® cross-fluted fills are designed for high efficiency and for meeting high effluent standards. Adjusted to the application, a...

Also by Enexio UK Ltd

Enexio UK Ltd address and contact details

Enexio UK Ltd
Hamilton House
5 Sketty Close
Brackmills Industrial Estate
Northampton
NN4 7PL
Tel: 0845 003 9114
Fax: 0845 003 9115
View on map
 
 
Not found what you're looking for? View other options

Ask Enexio UK Ltd about

Largest trickling filter project has low carbon rating