Context

Siltbuster’s infrastructure water treatment specialists were approached by Morgan Sindall Infrastructure to support with a water treatment system for concrete removal works on a major motorway project in Hampshire.

A drainage pipe under the M27 had become filled with concrete during works to upgrade the road to a smart motorway.

The blockage was causing surface water to collect in nearby areas, and works were required to remove the concrete using coring equipment.

This meant that highly alkaline run-off water from the works could end up in local watercourses, requiring it to be treated before it could be safely discharged.

Challenge

The site presented several challenges with logistics and access, and compliance and reliable setup needed to be at the core of the solution.

The criticality of the works and the tight space meant the client could not afford any down time or delays due to insufficient water management.

Due to the location of the drainage pipe, the water treatment system had to be set up in a nearby woodland adjacent to the works.

Solution

To reach the site, equipment had to pass under two low bridges with 3.7m clearance – but the height of the Siltbuster equipment alone was 2.6m, making it a close fit. Siltbuster sourced transport with a low bed height to ensure safe clearance when getting close to the installation site.

The precise location of the installation was inaccessible by road, so equipment was placed on site using a HIAB crane. This operation had to be carried out carefully so as not to damage nearby trees.

The Siltbuster team looked for a solution that could fit in a very tight space, was proven to be reliable and required minimal involvement and maintenance effort from the site teams.

Siltbuster worked closely with pumping specialists from Selwood, a sister company in the Workdry International group, from early engagement until completion of the project which would be operational for 10 weeks.

The solution was a pH adjustment and sediment control system, with Selwood electric pumps as they are more eco-friendly than diesel alternatives, used to transfer the water from the works into the treatment system. The average flow rate was around 5m3/h with level of pH of the infeed water of around 12.

The water was treated with a Siltbuster DS4 mix tank with controlled dosing of carbon dioxide, and FB50 lamella clarifier, designed and manufactured at Siltbuster’s HQ in Monmouth before being transported to site, where they operate on a plug-and-play basis.

In this type of solution, the water is pumped into the DS4 tank where an integrated probe and pH controller monitors the pH levels of the water and automatically controls the CO2 dose rates. When the pH level reaches neutral levels (6-9) water is transferred into an FB50 lamella clarifier where it flows upward between inclined plates.

The cement and coarse particles settle on the plates and slide down to the sludge collection area where they can safely be removed.

Result

The customer reports satisfaction with the system. Discharge water quality is within the expected range, and using a reliable Siltbuster and Selwood system will reduce costs for them in the long run.

The customer had a monitoring system installed in the watercourse which monitored the water quality both upstream before treatment, and downstream after treatment. This showed discharge water quality was in fact better than the upstream water quality.