Sector experience Water / wastewater
Services provided Design
Design and build
Installation
Upgrading
Client Severn Trent
Contractor Mott MacDonald Bentley
Year completed 2018
 
 

Context

Despite reductions in the amount of phosphorus entering rivers from WTWs, it is still the main cause of water quality failures.  Due to the requirements of the Water Framework Directive, it is expected that over 700 wastewater treatment works will require Phosphorus removal during AMP7.

Solution

The Pile Cloth Media Filter was developed by the Mecana company in Switzerland during the 1990s, with over 50,000 m2 of cloth now installed around the world. ELIQUO HYDROK brought this technology to the UK in 2013 and since this time have been at the forefront of its development. The largest ever installation at Deephams Wastewater Treatment Works (Thames Water) in 2014, treats up to 4200 l/s, and the world’s first large-scale two-stage application at Cirencester WTW (Thames Water) in 2016 is part of the Chemical Investigation Programme trials. This trial clearly demonstrated the capabilities of the Mecana process. With ferric salt dosing, it proved able to achieve <0.1 mg/l Total Phosphorus discharge continuously and reliably. No other process in these Nationwide trials proved capable of emulating this achievement.

Work undertaken

Severn Trent Water has committed heavily to the technology during AMP6 with some 11 projects deploying the Mecana process, one of these being at Goscote Wastewater Treatment Works, serving Walsall in the West Midlands. This site requires a significant upgrading due to the imposition of a stringent new ammonia consent, a 0.2 mg/l Total Phosphorus consent (the lowest in the Severn Trent Water region during AMP6), and a tight iron consent of 2.5 mg/l. The design team were subject to a series of challenges, including the presence of mine workings, cost reductions and the possibility of ‘out performance’ to deliver 7 ODI points worth £7m to Severn Trent Water. A key part of this success is the adoption of a two-stage Mecana installation with iron salt dosing, which when commissioned in early 2019, will be the largest such application in the world, treating 719 l/s; ELIQUO HYDROK are providing and installing the four flocculation tanks, six SF21/105 Mecana units and all the associated pipework.

Outcome

ELIQUO HYDROK worked closely with the main contractor, Mott MacDonald Bentley, and Severn Trent Water throughout the project to ensure the project delivers high quality effluent at the right price.


Context

Despite reductions in the amount of phosphorus entering rivers from WTWs, it is still the main cause of water quality failures.  Due to the requirements of the Water Framework Directive, it is expected that over 700 wastewater treatment works will require Phosphorus removal during AMP7.

Solution

The Pile Cloth Media Filter was developed by the Mecana company in Switzerland during the 1990s, with over 50,000 m2 of cloth now installed around the world. ELIQUO HYDROK brought this technology to the UK in 2013 and since this time have been at the forefront of its development. The largest ever installation at Deephams Wastewater Treatment Works (Thames Water) in 2014, treats up to 4200 l/s, and the world’s first large-scale two-stage application at Cirencester WTW (Thames Water) in 2016 is part of the Chemical Investigation Programme trials. This trial clearly demonstrated the capabilities of the Mecana process. With ferric salt dosing, it proved able to achieve <0.1 mg/l Total Phosphorus discharge continuously and reliably. No other process in these Nationwide trials proved capable of emulating this achievement.

Work undertaken

Severn Trent Water has committed heavily to the technology during AMP6 with some 11 projects deploying the Mecana process, one of these being at Goscote Wastewater Treatment Works, serving Walsall in the West Midlands. This site requires a significant upgrading due to the imposition of a stringent new ammonia consent, a 0.2 mg/l Total Phosphorus consent (the lowest in the Severn Trent Water region during AMP6), and a tight iron consent of 2.5 mg/l. The design team were subject to a series of challenges, including the presence of mine workings, cost reductions and the possibility of ‘out performance’ to deliver 7 ODI points worth £7m to Severn Trent Water. A key part of this success is the adoption of a two-stage Mecana installation with iron salt dosing, which when commissioned in early 2019, will be the largest such application in the world, treating 719 l/s; ELIQUO HYDROK are providing and installing the four flocculation tanks, six SF21/105 Mecana units and all the associated pipework.

Outcome

ELIQUO HYDROK worked closely with the main contractor, Mott MacDonald Bentley, and Severn Trent Water throughout the project to ensure the project delivers high quality effluent at the right price.


Interested in this project?
Call 01726 861900
OR
 
 
 
Downloads
  • Eliquo Hydrok Tertiary Filtration
    Eliquo Hydrok Tertiary Filtration
    2.32MB
    Download
  • EloPhos® phosphate reduction & recovery
    EloPhos® phosphate reduction & recovery
    939.54KB
    Download
 
 
 
Enquire
 


Related entries

  • ELIQUO HYDROK: IFAS enhanced biomass fixed bed system
    IFAS enhanced biomass fixed bed system
    ELIQUO HYDROK
    The Hydrok IFAS™ (Integrated Fixed-Film Activated Sludge) system utilises Biotextil Cleartec media for the growth of biomass for the treatment of effluent. Biotextil Cleartec is a polypropylene product that creates a large...

Also by ELIQUO HYDROK

ELIQUO HYDROK address and contact details

ELIQUO HYDROK Ltd
Warren Road
Indian Queens Industrial Estate
Indian Queens
St Columb
TR9 6TL
Tel: 01726 861900
Fax: 01726 862008
View on map
 
 
Not found what you're looking for? View other options

Ask ELIQUO HYDROK about

Mecana pile cloth media filters for phosphorus removal